Georgia: Sustainable Urban Transport Investment Program - Tranche 3
Project information |
Request number |
2018/1 |
Project name |
Georgia: Sustainable Urban Transport Investment Program - Tranche 3 |
Loan number |
Loan 3063 |
Country |
Georgia |
Summary
A third request for compliance review for the Georgia: Sustainable Urban Transport Investment Program - Tranche 3 was received by the Compliance Review Panel on 21 June 2018. The complaint is about Subproject 1: Tbilisi-Rustavi Urban Road Link (section 2) which involves the modernization/upgrading of a 6.8 km road from Phonichala to Rustavi.
Progress Report
Steps and Milestones |
Date |
Remarks and Attachments |
|
CRP received a request for compliance review (the complaint) |
21 June 2018 |
Request for compliance review [PDF] |
|
CRP informs the complainants, borrower, ADB Board member representing the country concerned, and ADB Management about receipt of the complaint |
25 June 2018 |
|
Step 1. Requesting Management Response |
|
|
CRP's initial assessment of the complaint |
27 June 2018 |
Completed |
|
CRP's assessment |
27 June 2018 |
Complaint falls within the mandate of the compliance review function. |
|
CRP forwards the complaint to ADB Management for response |
27 June 2018 |
Completed |
Step 2. Determining Eligibility |
|
|
Eligibility of complaint reviewed by the CRP |
|
Reviewed. Eligibility mission held from 8-10 July 2018. |
|
CRP report on its review of eligibility submitted to ADB Board. CRP deems the complaint eligible but does not warrant a separate compliance review. |
23 August 2018 |
Eligibility Report in
English and in
Georgian
|
|