Summary
A request for compliance review for India: Rajasthan Urban Sector Development Program was received by the Compliance Review Panel on 19 August 2022. The complainants have alleged that due to indiscriminate construction, their properties have been damaged.
Progress Report
Steps and Milestones |
Date |
Remarks and Attachments |
|
CRP received a request for compliance review (the complaint) |
19 August 2022 |
Request for compliance review [PDF] |
|
CRP informs the complainants, borrower, ADB Board member representing the country concerned, and ADB Management about receipt of the complaint |
26 August 2022 |
|
Step 1. Requesting Management Response |
|
|
CRP's initial assessment of the complaint |
26 August 2022 |
Completed |
|
CRP's assessment |
26 August 2022 |
Complaint falls within the mandate of the compliance review function |
|
CRP forwards the complaint to ADB Management for response |
26 August 2022 |
ADB Management's response expected on or before 26 September 2022 |
Step 2. Determining Eligibility |
|
|
Eligibility of complaint reviewed by the CRP |
|
Completed |
|
CRP report on its review of eligibility submitted to ADB Board. CRP deems the complaint ineligible and does not warrant a compliance review. |
21 October 2022 |
Eligibility Report [PDF] |
|
|