Pakistan: Balakot Hydropower Development Project
Summary
The complainants assert that the provisions outlined in the Land Acquisition and Resettlement Plan (LARP) for the project were not followed, among other issues.
Progress Report
Steps and Milestones |
Date |
Remarks and Attachments |
|
CRP received a request for compliance review (the complaint) |
21 February 2024 |
Request for compliance review [PDF] |
|
CRP informs the complainants, borrower, ADB Board member representing the country concerned, and ADB Management about receipt of the complaint |
26 February 2024 |
  |
Step 1. Requesting Management Response |
|
|
CRP's initial assessment of the complaint |
26 February 2024 |
Completed |
|
CRP's assessment |
26 February 2024 |
Complaint falls within the mandate of the compliance review function |
|
CRP forwards the complaint to ADB Management for response |
26 February 2024 |
ADB Management's response received on 26 March 2024 |
Step 2. Determining Eligibility |
|
|
Eligibility of complaint reviewed by the CRP |
15 May 2024 |
Completed |
|
CRP report on its review of eligibility submitted to ADB Board. CRP deems the complaint ineligible and does not warrant a compliance review. |
27 May 2024 |
Eligibility Report [PDF] |
|
|