India: Assam Solar Project
Summary
The project aims to boost Assam's solar PV capacity by constructing a 500 MW facility in Karbi Anglong and a 250 MW plant under a PPP model. It includes a joint venture for a pilot battery storage installation and improvements to local electricity distribution. The complaint concerns the displacement of a tribal community and the threat to their cultural heritage and livelihood.
Progress Report
Steps and Milestones |
Date |
Remarks and Attachments |
|
CRP received a request for compliance review (the complaint) |
4 November 2024 |
Request for compliance review [PDF] |
|
CRP informs the complainants, borrower, ADB Board member representing the country concerned, and ADB Management about receipt of the complaint |
12 November 2024 |
  |
Step 1. Requesting Management Response |
|
|
CRP's initial assessment of the complaint |
12 November 2024 |
Completed |
|
CRP's assessment |
12 November 2024 |
Complaint falls within the mandate of the compliance review function |
|
CRP forwards the complaint to ADB Management for response |
12 November 2024 |
ADB Management's response is expected on or before 12 December 2024 |
Step 2. Determining Eligibility |
|
|
Eligibility of complaint reviewed by the CRP |
Ongoing |
|
|